Tuesday, August 6, 2013

Up to 50% of newly available wind power is wasted with no place to go

The Miami Herald

Newly available wind power often has no place to go

 
Sunrise at a field of wind turbines which stand nearly 300 feet high
Bob Chamberlin / Los Angeles Times/MCT
Sunrise at a field of wind turbines which stand nearly 300 feet high
The windswept prairies of the Midwest are undergoing an energy transformation the electric grid can’t handle.

Wind turbines tower over rural vistas in the heartland, where the clean energy source is becoming increasingly popular with utility companies that face state-mandated renewable energy standards. Unfortunately, the nation’s aging power grid is hampering those efforts.

At the end of last year, installed wind-generation capacity totaled 60 gigawatts nationwide – 5 percent of the nation’s production capacity – according to data from the U.S. Energy Department’s National Renewable Energy Laboratory. Another 135 gigawatts of potential wind production awaits development and connection to the grid, according to industry data.

“There hasn’t been a lot of investment in the grid for the last two decades,” said Michael Goggin, a senior analyst at the American Wind Energy Association, the industry’s main trade group. “We just don’t have a strong grid that’s built out in the parts of the country where there are a lot of wind resources.”

The transmission grid was built a generation ago for coal, nuclear and hydropower plants without renewable energy in mind. It makes transmission from wind farms in rural areas difficult and costly.
The shortfall in transmission capacity hasn’t gone unnoticed.

Gil Bindewald, a project manager at the Department of Energy, said decision makers had to consider policy, technology and financing when dealing with transmission issues.

“There is no silver bullet solution for effectively integrating renewable sources of energy such as wind onto the grid,” Bindewald said.

The growth of the nation’s wind-power supply is evident on a remote stretch of Kansas Highway 23, where the spinning blades of wind turbines quickly surround motorists near the town of Cimarron. The site, which has 57 turbines spread over 16,000 acres of leased farmland, is capable of powering 40,000 homes with 131 megawatts of production.

But Duke Energy and Sumitomo Corp., which brought the project online in June 2012, face significant congestion as they try to bring that energy to the market.

Greg Wolf, the renewables president at Duke Energy, wouldn’t comment on the level of congestion, but he said the bottleneck was noticeable.

“Because it’s new and because there’s variability in wind versus a traditional gas-fired unit, there’s been a learning curve here,” Wolf said. “Not to mention the fact that we’ve added a large number of new megawatts at a quick pace.”

Wolf said deficiencies in the grid and differing state policies on the placement of transmission lines were prime causes of congestion.The Southwest Power Pool, the Federal Energy Regulatory Commission’s regional transmission operator in the area, said it experienced four to five transmission curtailments – periods of high congestion that shut down wind units – per week. Over the past eight months, those curtailments have affected up to seven sites.


“They’ve connected to the system in our region ahead of planned transmission upgrades,” said Southwest Power Pool’s director of system operations, Don Shipley. “Some of the wind farms have seen fairly significant impacts of up to 50 percent of their projected production.”

In other words, a lot of the power those farms were expecting to generate isn’t making it to the market.

Shipley said the electric market and the wind farms were losing money because of the curtailments, as the pool is unable to sell power that the grid is incapable of transmitting.
...
Opponents of wind energy say that even a nominal increase in transmission costs will mean higher utility prices for consumers...

Utilities and policy makers often blame transmission policy for delaying grid expansion. For PacifiCorp, permitting takes at least three years at the federal level alone. Including the permitting process, constructing transmission projects can take up to eight years.

As with the grid, the policies were developed when utilities owned the generation and transmission infrastructure required to deliver electricity.

“We’ve transitioned to a kind of market structure with competitive markets for electricity, and the same company doesn’t own both the transmission and generation,” said Goggin, of the American Wind Energy Association. “The policies that were able to build transmission under the old system don’t work under the market system.”
...
For the wind industry, tackling transmission is the key to tapping a vast resource. If the industry doesn’t increase capacity, utilities might be stuck watching their resource blow away.

“There’s enough resource there to power the United States a dozen times over by conservative estimates,” Goggin said. “A lot of that resource is concentrated in the middle of the country, far from where people live. There’s extremely cost-effective wind left out there. We just can’t tap it, because we haven’t built out the transmission system.”

2 comments:

  1. Classical failure to think ahead. Still one more Fire, Ready, Aim failure gambit brought to you by your not so friendly government.

    Their solution is to do more of the same but on a larger scale. That it hasn't and won't work is a feature not a bug. It gives them more reason to expand on what has demonstrably failed. They take the size of the failure is a measure of their success.

    We the People are to pay and pay and pay unto the seventh generation and beyond. All to support the political elite as they dance, prance, and posture that they are "doing something."

    THIS is unsustainable! When all available wealth has been consumed and it has been made impossible for the producers to create more wealth, it will end. See the history of Rome for instructive detail.

    ReplyDelete
  2. Along with choosing and installing residential wind turbines, a homeowner also needs to choose the option to save the energy for future use. The wind energy can be stored using batteries or a grid.

    ReplyDelete